NEW CONNECTION, CHANGE OF NAME, CHANGE OF TARIFF AND REDUCTION / EXTENSION OF LOAD



Reference  =   General System Description


1-1 For processing application ns for new connections, these are divided into following five categories:

-CATEGORY-1

General connections for load upto 15 KW

-CATEGORY-2

a) Tariff B -1 & B - 2 for industrial supply tubewell connections at 400 volts for load upto 70 KW.

b) Other supplies an d general connections above 15 KW and upto to 40 KW at 400 Volts.

CATEGORY-3

a)Tariff B-2 for Industrial supply at 400 Volts for load above 70 KW but not exceeding 500 KW.
b)Tariff C-1 for Bulk Supply at 400 Volts.
c) Other supplies and general connections above, 40 KW but not exceeding 500 KW.

CATEGORY-4

a)Tariff B-3 at KV or 33 KV for load not exceeding 5000 KW.
b)Tariff C-2 for Bulk Supply at 11 KV or 33 KV.
c)Other supplies and general connections at 11 KV or 33 KV for load not exceeding 5000 KW.

CATEGORY-5

a)Tariff B-4 for Industrial Supply at 66 KV or 132 KV or 220 KV for all loads.
b)Tariff C-3 for Bulk Supply at 66 KV or 132 KV for all loads.
c)Other supplies and general connections at 66 KV or 132 KV 220 KV for all loads.
Procedure




COMPANY / CIRCLE / DIVISION / SUB-DIVISIONAL OFFICE


Procedure for New connection, Change of Name, Change of Tariff and Reduction / Extension of Load Code Page cp -02 3 of 88